MRP run agnst remaining PIR

Hi gurus,

In strategy 40.

I gave PIR for 100 units and CIR for 50 units. Result is pln ord of 50 units. In MD62 we can see 50 units remaining req.

Now when Iu2019m running MRP agn I donu2019t want MRP to consider this remaining PIR req. What setting I shd make in configuration to achieve this?

Kindly assist.