Not able to create the delivery for all the line iteme mentioned in the PO

Hi Sap Gurus.

I have created the Po for 4 line items , for the same i tried to create the Delivry reference to PO, But its fetching only one line item into delivery .

Could you please help out inthis issue.

I have checked the following prerequisites.

I have checked all the Below pre requisites and everything is maintained correctly .

1) Shipping points of all the four line item is same.

2) The Delivering plant of all the line items is same

3) Check the shipping conditions of all the line items is same

4) Check the loading group of the two items.

5) Delivery date for all the line items is same.

6) Shipping route is same for all the item is same.