on 06-13-2011 4:11 AM
Hello
We have MTO with Production Order cost estimate for valuating invendtory.But the value of GR is not matching with Production Order cost estmate though strategy is "2"-with which its valuated.The estimate does not have any majaor itemisation except Activity cost-which is unchanged.How do i find the the value with which GR is done.AN order cost estimate no is saved in EBEW.WIll this give me trail of the itemisation with values & how can i get the trail.
Hi Ajay,did u find answer already?
i also need to analyze cost component for MTO sales order item,dont know which table save that data.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
What is setting in your Requirement Class in the Field "Valuation?? Is it M??
And have you ticked on "Without Val Strategy" check box in your req class??
If you have not ticked - Then following strategy applies
1. Price from exit
2. Sales order cost estimate
3. Prod order cost estimate
4. Std cost estimate from Mat Master
Please check on these lines
br, Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi SR,
- Value GR is not match with the order, here are my basic question
-
> Are you using material in the standard price or moving?
-
> Are man days estimated is same with the actual GI?
If there is different than cost estimation would not be the same with the actual GR.
- Find the the value with which GR is done, I'm not sure about the question here & correct me if I'm wrong.
If you want to search whether GR is done or not you should check by the Order in module PP
- How can i get the trail, if you want to get the trail over cost and until sales order in placed, I think it has to be a custom program
Hope helps
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Using the material with Std Price "S".
When we use the Porduction Order cost estmate for GR valuation in special stock-System generates a cost estimate.
Is it possible for me to find the itemisation of this cost estimate from any table I have tries KEKO/CKIS-but it seems these are for Std Cost estimate.Are there any tables for me to find itemisation of specific Prodn Order cost estimate-which is stored with Old Production Order cost estimate.If i new see itemisation of prodcution Order-the actual cost goes into variance.This is major worry.How do i find this,
Hi,
Your material is managed on S or V in material master. If its S then the standard cost estimate is the price at which GR happens in production order.
Regards,
Divraj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.