Creation of Technical POD nd Assigning Meter to it in Past Date

Former Member
0 Kudos

Hi,

The requirement is to create a technical point of delivery and assigning a meter to it at a past date.

I tried this manually through EEDM09 transaction as well however it doesnot allow in past date.

Is any confirguration required to achieve this?

It will be nice if you can advice with some way to achieve this functionality

Thanks,

Sarvesh

1 REPLY 1

Former Member
0 Kudos

Hi Sarvesh,

It should be possible to assign a technical POD to a meter in a past date.

Have you checked the from dates in the header data of the POD.

and also the date of allocation in the 'Alloc' tab.

The meter should be having 'Installed' status for allocation.

Please revert back for any clarifications.

Cheers,

Rakesh..