i want to issue one drum of 280 Liters gresse and will use in the repair and maintenance of multiple orders so how i can distribue the cost of 280 liters on different orders becuase i get issue drum at once from stores

(; I am issuing from store a drum of grease u201C208 Lu201D. this drum can be used for letu2019s say 200 orders. How those distribution can be done?!)

regards

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

either you have to create order while doing the maintenance and reserve the same. or you have to post the consumption equally directly against the cost center

regards

thyagarajan

Former Member
0 Kudos

one problem stores issue me one drum and i used that oil of drum in different orders than how i can distrubute that 10 liter i used in one order and 15 liter in other order is there any other way ???

former_member187991
Active Contributor
0 Kudos

hi

i think there is no other way, you have to create order for the same

regards

thyagarajan