Sir,

while creating a work center for quality inspection what are the parameter we want to give for example in

in basic data tab what are filed value for usage and standard value key

and what are the formula we want to give in other tabs

psl clarify

Faisal

Accepted Solutions (1)

Accepted Solutions (1)

former_member1362664
Contributor
0 Kudos

Hi,

In T code CR03 Put work center code with plant and category (0008) .

In basic data select usages (002) And select standard value key (SAP0).

and there are no need to define formulas in work center for quality inspection.

Regards

Vivek

muhamed_faisal
Active Participant
0 Kudos

hi

You mean work cetner catagory-0008(Processing unit)

and if we go to t code op40 application in this catagory is only for recipes

Please confirm

Faisal

former_member1362664
Contributor
0 Kudos

Hi,

Yes. You are right this is applicable for recipes.

In case of Inspection plan if your work center is Machine oriented select (0001).

And if In case of Inspection plan if your work center is labor oriented select (0002).

Regards

Vivek

Answers (1)

Answers (1)

Former Member
0 Kudos

From QM point of only control key & cost center is imp.

Do not enter formula as its not relevant to QM.Rest of the things are related to PP-PI