Hello All,

When I execute MCPM report , in input screen i enter material No, plant , date ( period to analyze ). I am not getting what is that

date parameter. Which date does the system is considering ( order start date, order finish date, doc date, posting date , scheduling dates etc ) while executing this report .

Please reply

Rgds

Prabhu

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

It should be the actual finish date, obtained from the order confirmation. Field GLTRI in CAUFV.

Regards

Former Member
0 Kudos

Thanks for your valuable input