Scheduling operations

Former Member
0 Kudos

Hi Friends

we had one prodcution orders and 10 operation are there.

First operation 0010 starting on 11.06.11 at 7.00 hrs only operation duration which is 1085 min(18 hrs).

capcity of this operation workcenter is 4.76 hrs break time 1 hr. so when i am claculating it has to finish on (18/4.76=3.78 aprox 4 days) but the sap is showing its tear down on 22.06.11. 7:53 hrs.

How come ?

if i want to complete this on 15.06.11 what i have to do ?

Regards,

srihari.M

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member1362664
Contributor
0 Kudos

Hi..

In addition of this you can check the routing data in this you can tick on overlapping data and put 1 on overlapping qty and then check.

Regards

Vivek

Former Member
0 Kudos

Hi

Already we had maintained in routings-. overlapping continous production and min ahead qty:1

Regards,

srihari.M

Former Member
0 Kudos

Hi,

Have you checked the factory calendar assigned to the work center? If there were off days between start and end date, duration of the operation lasted long.