Priority Change in PM Order

Hi PM Experts,

I got the same set up for both PM Notification and Order in terms of priorities.

When I change the priority in the Notification, the Required Start/End dates change accordingly. But when I change the priority in Order dates doesnt change. Could somebody please suggest why?





Only when entering the priority on initial screen will this priority affect the order dates (that is when creating the order). Subsequent changes will not adjust dates as it does on a notification - because the order is subject to scheduling no adjustment is done based on changed priority.

You could implement some logic to adjust the dates through exit IWO10012.