According to my knowledge, the sequence of phases in cpro (4.5) cannot be changed when the phases are already released.
Is this true? For exceptional cases, is there any change to achieve this? Maby via BAPI?
Hi Daniel;
I have been tested this sequence a lot of times, when project & phases are released are imposible to change.
Only when the phases are "created" can changed.
Error message "DPR_PHASE008".
Hope this help you.
Best regards.
Mariano