Hello,
I know that in PM order there is possibility to assign equipments from the object list to operations.
My question is: what is relation between object and operations.
It is possible to assign several equipments to an operation?
Thanks,
Laurentiu
Hi,
You can only assign each equipment once, each equipment (or other object) can be assigned to one or more operations.
[SAP Help|http://help.sap.com/saphelp_erp60_sp/helpdata/en/5b/ae48624b8611d182ba0000e829fbfe/frameset.htm]
-Paul