on 06-10-2011 7:27 AM
Dear all experts,
I am trying to do confirmation for my production order in CO11N. However, i have received this error meesage when i am trying to save / post.
"*Account ***** requires an assignment to a CO object*"
Message no. KI248
= secondary cost element
Base on my understanding, Secondary cost element will not assign to CP Object.
Is there any solution ?
Thank you.
Problem solved with I/O that accidentally change posting to Production Order to Statistical I/O, that is why the posting to Production Orders is changed to statistical cost object
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Go to OKB9.
Enter your company code.
Select any cost element and check Profit center associated with it..
Use that profit center in MM
and re-execute confirmation.
let us know if you able to post the cofirmation
cheers,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check with your FI-CO consultant regarding the Co assignement in OKB9 for your cost element
Regards
Anupam Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.