Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Condition from PO into CCS in ML

Hi experts,

Currently, we have the following scenario. We have a material X, which consists of the following costs:

- the main cost of the material: 20 EUR

- the import duty of the material: 2 EUR

Well, I have managed to create a standard cost estimate, using the condition type from PO, and assign that import duty into its own cost component structure. So, in the CCS, i have:

- Direct material: 20

- Import Duty: 2

However, in the ML view, whether it is CKMCCD or CKM3N, this import duty cost component is empty. Moreover, the client needs to be able to analyze the variance from the import duty.

Have anyone ever deal with such cases?

Would you guys mind telling me what is the best approach to my case?

Thank you very much in advance

Best Regards,

Erwin Hartono

Former Member

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question