GB NI costs - schema change

Hi all,

I am looking through an old note that I would like to implement, oss 323846.

The note mentions adding a new parameter COST to function GBPSC; as suggested by the note, it says to add to par3.

However, when I do this, it says it is an incorrect value for parameter 3??

Can anyone guide me as to how the parameters should be presented, and do I need parameter INIT aswell?

Former Member
replied

Hello

Are you using XDEC for NI cost distribution?

If so, then the old NI cost distribution solution should not be active

in your schema. Parameter 1 of GBPSC should not be set to COST in any

part of your schema and therefore /VNC and /VNS should not be created.

If not, then the old NI cost distribution solution should be active

in your schema. Parameter 1 of GBPSC should be set to COST at the start

of your schema and therefore /VNC and /VNS should be created and will

need to be moved to RT by PCR GBP1.

Please have a look at the documentation of the payroll function GBPSC

as well.

Thanks and Kind Regards

Ramana