Conversion of Price control from V to S when material ledger is active


We use material X is with price control S and price determination 2 in plant 1000 and same material with price control V and price determination 2 in plant 2000.

Both plants 1000 (belongs to Company Code 1001) and 2000 (belongs to Company Code 2001) already went live

In Plant 1000 is Material Ledger and actual costing is active

In Plant 2000 is Material Ledger is active and actual costing is not active.

Both plants we have several sales orders and material transactions.


If I want convert the plant 2000 price control from V to S and price determination from 2 to 3 when several mateerials exists in plant 2000.

What are the steps I need to do now for conversion.



Hi Raj,

You should use transaction CKMM.Please check the note 703604 which provides you a detailed information

about how to change the price determination control from 2 to 3.

Please take also a look at the note 384553 which provides you further details about transaction CKMM.

Best regards,