cancel
Showing results for 
Search instead for 
Did you mean: 

Stability study

former_member184574
Active Contributor
0 Kudos

Hi gurus,

I am performing a stability study test.

I have created the inspection plan for the material with the following.

Usage 9 Material check

Status 4 Released (general)

Insp. Points Inspection based on samples

Dynamic mod. level at Char level

and assigned a Modification rule.

After i started creating the notification for the material in QM02.

Created the initial sample

Created inspection lot and UD taken.

specified storage conditions.

While creating the testing schedule it asks for maintenance plan.

when creating the maintenance plan in IP01 the following error message is coming.

"The physical sample 900000100 is not part of stability study"

We are unable to proceed further.

Kindly advice

Regards

Vinamrath

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Use engineering workbench for this. From there you can directly use packages and strategies.

Or, create inspection plan in QP01 and goto CWBQM to include strategy and packages.

In CWBQM, go to inspection plan header level, scroll right way and you will find strategy (Same line as lot size, usage etc). For packages, select the task list and go to operation, from there select maintenance package (Task list--> maint package in overhead bar)

Your stability study should work now.

Answers (0)