on 06-09-2011 10:06 AM
Hi experts ...
In maintenance order , depending on equipment , the planning plant gets defaulted . If Equipment is installed in another FL whose planning plant is different , the order's planning plant doesn't change (Greyed) . Is there anyway to change planning plant in orders
NPB
hi
you can only change the planning plant while creating the maintenance order only. in the initial screen (IW31) after entering the equipment specify the different planning plant and enter it will allow the same
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
We have maitenance and planning plant same .Equipment was in maintenance plant XYZ and planning plant XYZ earlier . Now the same equipment is in maintainance plant ABC and planning plant ABC . In order , I am able to change maintenance plant to ABC , but unable to change the planning plant to ABC .
If I do not change planning plant and change only maintenence plant , what are the effects in cost reporting ? Since ultimately cost is settled to equipment cost center (which is now changed to ABC cost center) , I feel there will not be any effect . Old planning plant may only affect search right ? ....Please advise ...
NPB
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.