Capitalised value from legacy system

My client tried capturing all costs from previous years i.e. before launch of PS from a legacy system. So for this they created WBS for earlier years. Posted actual costs through Manual Allocation through FI postings. For this they created a dummy cost center and a dummy cost element.

After manual posting of actuals this was captured in PS reports.

They then settled the costs for those WBS of previous years to the same dummy cost center and this was how costs are captured in PS for legacy WBS elements.

There is a column in PS report which captures Capitalised value and costs which are settled from WBS to AuC through CJ88 are captured in this column.

Now the problem is costs capitalised for those WBS of previous years could not be captured as these are settled to cost centers. How to proceed now to correctly report this value in PS?