planning all MRP relevant material together

former_member186193
Active Contributor
0 Kudos

Dear All,

I am bit confused because i want to plan all MRP relevant material in a plant together and i am not able to do that. Can someone please tell how to configure that and plan all material together. I have AFS add-on with standard SAP 6.04.

Thanking you in advance.

Regards,

Alok Tiwari

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member186193
Active Contributor
0 Kudos

THANKS..... CLOSED

asik_shameem
Active Contributor
0 Kudos

Hi,

I don't find anything tricky here. It's just straight forward.

In trx MD01 give the relevant plant and run the MRP. If it is for more than one plant, define the scope of planning in trx OM0E.

former_member186193
Active Contributor
0 Kudos

Hello,

I have only one plant, so it means i need not have scope of planning but i am getting an error "Please check the destinations for parallel MRP" Please advice.

Regards,

Alok Tiwari

asik_shameem
Active Contributor
0 Kudos

Hi,

If you running MRP with Parallel processing, you should define Parallel Processing in trx OMIQ. ie. No of sessions should be defined.

Otherwise you should uncheck the field Parallel processing in MD01.