Impact of Planning horizon configuration

former_member337527
Participant
0 Kudos

Hi,

I have changed the planning horizon of a plant via OMDX transaction. Please let me know how I can check the impact of this in the business? Where will this be reflected? Can this change be seen during order creation? If so, please provide the details

Thanks & Regards

Jegashree

Edited by: Jegashree on Jun 9, 2011 8:51 AM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi ,

For example :

Value in planning Horizon is 150 u maintain in OMDX or OPPQ

And u place order in md61 after 150 days .

Independent requirement is generated for require order in md04

Run MRP through md02

Processing Key : NETPL

Result will be display in md04.

u find that there is no planned order generated for the required order.

I hope your idea is clear. If any problem pl revert

Regards

vinod

former_member337527
Participant
0 Kudos

Hi,

I am able to do it correctly now. Thank you all

Regards,

Jegashree

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Sir,

Planing horizon period is being maintained in OMDX or OPPQ.

Three types of planing types is being there

NEUPL-Its is being run for first time when the sysyetm beocmed Go live.It generated planing files entries for all the material whether it is being planned or not, ireespective of planing horizon days.

NETCH-Net Change in planing Horizon-When MRP will rum, it will consider only those material whose RLT is lying in this period or demand is in this period.

NETPL-Net change in planing-It will consider all the perod irrespective of planing horizon time

RRevert back for anydoubts

Regards

Bhupendra Singh

former_member337527
Participant
0 Kudos

Hi,

Thanks for the reply.I tried doing as Vivek said.

Placed a demand outside the planning horizon via md61 and tried doing the MRP run. Actually it plans for the MRP. Kindly let me know how to cross check this??

Thanks & Regards,

Jegashree

Former Member
0 Kudos

When you say you placed outside the planning horizon, may I know how what is the value you have maintained for the planning horizon & on which date did you place the demand on (computation has to be based on working days)?

Did you run MRP using NETPL ?

Upload screenshots of MD61 & MD04, along with OMDX details.

Former Member
0 Kudos

A simple test, place a demand (eg: a independent demand via MD61) outside the planning horizon, execute MRP with processing key as NETPL. MRP will not plan for this demand.

Hope it clarifies.