how to upload item and project structure(phase and task)

Former Member
0 Kudos

Need to upload data for project ,phase ,task,item.

Problem we are facing is if we upload item using RPM_DX_ITEM it generates project name so cant upload project details with phase nad task).can you please suggest?

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hello All ,

I am trying to use this report to create the items . Niether does it create the item nor it displays any error in the output. I am trying to find the reason in debug but no success yet.

The file structure i had copied from the same transaction.

Any idea

Thanks

mariano_sabiche
Active Participant
0 Kudos

Hi Narenthakkar;

Please uncheck the Field "CREATE_CPROJECT" and the Item will not create a Project in project Management.

Hope this help you.

Best regards,

Mariano

amit_maheshwari2
Contributor
0 Kudos

RPM_DX_ITEM is used to upload items.

To upload the project along with phase and tasks, use the transaction RPM_DX_PROJECT.

Regards

Amit