Fixed and Variable actual activity price calculation

Hi

When I execute KSII - actual price calculation on production cost centre group system shows the following results :

Total amount of fixed cost element group / actual hours = fixed price of activity

Total amount of vairable cost element grous/actual hours = variable price of activity

and these prices updated in the respective fields of activity (MACHIN) for the production cost centres.

Q. How system is segregating that these are the fixed cost and this is the variable cost. Even splitting structure is not configured. Only one activity is here.

regards

imdad

Tags:
Former Member
replied

Hi,

Check the data in KP06 and KP26

regards

Waman

0 View this answer in context