on 06-08-2011 2:11 PM
Hi
When I execute KSII - actual price calculation on production cost centre group system shows the following results :
Total amount of fixed cost element group / actual hours = fixed price of activity
Total amount of vairable cost element grous/actual hours = variable price of activity
and these prices updated in the respective fields of activity (MACHIN) for the production cost centres.
Q. How system is segregating that these are the fixed cost and this is the variable cost. Even splitting structure is not configured. Only one activity is here.
regards
imdad
Hi,
Check the data in KP06 and KP26
regards
Waman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Waman,
Does this mean the activity dependent and independent cost elements planning that we do in KP06 will also be used to determine the fixed and variable portions for actual activity price calculation as well in KSII?
I thought the above KP06 based fixed and variable splitting is only used for plan price calculation KSPI only.
Please confirm which is true.
Imdad Hussain,
Fixed cost or variable cost is segregated in cost planning KP06. Attach below link of price calculation
http://wiki.sdn.sap.com/wiki/display/ERPFS1/Activity%20Reconciliation%20and%20Price%20Calculation
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.