on 06-08-2011 1:48 PM
Dear All,
I have some below doubts for t-code IP19-
1. Can we run this report in background? I have tried to do so but job status is always showing as only active
not finished status even though it was run for long time.No data is displaying.While in foreground
for same input parameters,ouput data is coming .Please clarify.
2. Can we export the output data of t-code IP19 to excel sheet?
3. What is use of "save" button in output of t-code IP19?
4.What is meaning of maintenance plan simulation?
5.Can we change the maintenance plan planned date in IP19 ? If yes,how?
Please clarify my above all doubts.Thanks in advance.
Rgds
Rajib
Hi,
You can export the Output to excel. Go to List => Export => Spread sheet. In the pop up window, select Excel option.
You can change the particular call date by clicking Fix Call up.
If you want to change even subsequent calls, then click Subsequent Calls.
Regards,
Maheswaran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.