Create SA refer PR

Dear Expert

I found some problem when I monitor by MD04.I explain you step by step

1) Create SA refer PR

2) Create source list refer SA , select option source of supply and 2 in Source List Usage in Materials Planning

3) Run MRP with MD01

4) After finished run MRP , I checked data by MD04 I found the PR quantity not reduce and SA delivery schedule line (SchLne) is not generate

Please advice me.

Best regards,

Tachaya O,