After confirmation automatic comes in BIN

Hi Experts,

After confirmation(cor6n) of material should come on storage type(901) and after doing LB12 it will come on storage bin.

But in my case after doing processing raw material to fert material through process order(cor1),confirmation(cor6n) .i.e

nothing but mov 103 GR for production.

So why without doing lb12 it comes directly to storage bin,do my system has automatic setting?