Hi All
We have an error in production order "Configuration of raw material still not included in pricing determination" . Please note we are using Variant configuration . Thanks in advance .
Regards
Ayaz
Get in touch with your costing or CO consultant to fix the valuation variant.
In OKKN, identify the costing variant which you're using, then in the valuation variant associated with it, go to material valuation tab & check if strategy sequence contains price from info-record, if not maintain the same & then check.