Hi Experts:
I have projects with two levels. Second level WBS elements have internal order assigned. I can't change it because of MM requirements. I would like to have availability control in my WBS elements and in my internal orders . However, the system issues a mistakes when you try to assign buget to internal orders assigned to WBS elements.
According to that mistake, internal orders assigned to WBS elements can not have budget because the budget is provided from the WBS element.
I know I can plan internal orders and spend budget when I plan them but it is not exactly that I need.
Would it be possible to make something about that?
Thanks in advance
Best regards
Jose
Hi,
Unfortunately this is standard SAP functionality
If a WBS element has a budget then the expenditure of any associated object e.g. Network/activity or Internal Order is
matched against the WBS element's budget.
For example, if you attach an Internal Order to a WBS element that order cannot be budgeted. Message KO414 presents if you try as you have found.
If you post against the I/O then the posting is considered against the WBS element's budget (the I/O cannot have budget
as it is assigned to the WBS element which controls budget)
regards
Waman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.