Hi

Can anyone suggest how to transfer planned orders generated from LTP(Long Term Plan) to Operational Plan?

Regards

Pradipta Sahoo

Accepted Solutions (1)

Accepted Solutions (1)

former_member184655
Active Contributor
0 Kudos

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Double click on the planned order in MS04 , new screen is open , in which one tab is there ---> convert planned order into production order. ---> click the same tab.

Regards

Vinod

former_member197663
Participant
0 Kudos

Hi

I am not able convert planned order to a process order from MS04 directly.

MS04 does not have the tab conversion from planned order to process order.

Please suggest.

Regards

Pradipta Sahoo

former_member184655
Active Contributor
0 Kudos

Dear Sahoo,

You can transfer the simulative planned orders to operative planning using T Code MD43.

Check this,

Copying the Long-Term Planning Results to Operative Planning

Use

Once you have optimized the results of long-term planning, you can copy them to operative planning.

It is not only possible to copy the demand program to operative planning, you can also copy the planned orders firmed in long-term planning per material using the MRP transaction Interactive single-item planning.

When copying the results to operative planning, you can set the system to create purchase requisitions and delivery schedules instead of planned orders for materials procured externally.

Prerequisites

You must firm the simulative planned orders you want to copy to operative planning. You can firm planned orders by:

Making manual changes

Using the planning time fence

Setting a manual firming date

If, when copying the data to operative planning, you want the system to create purchase requisitions or delivery schedules for materials procured externally instead of planned orders, enter the appropriate indicators in the Create pur. req. and Schedule lines on the initial screen of single-item, interactive planning (in MRP).

When copying the results to operative planning, the system does not carry out any source determination. If you want the system to create delivery schedules and purchase requisitions to which a vendor has already been assigned, you must maintain the necessary master data in the Purchasing menu before carrying out the planning run in long-term planning.

http://help.sap.com/saphelperp60_sp/helpdata/en/92/bf02af44bd11d182b40000e829fbfe/content.htm_

Regards

Mangalraj.S

former_member197663
Participant
0 Kudos

Dear Mangalraj

Thanks for your reply. Your suggested http://help.sap.com/saphelp_erp60_sp/helpdata/en/92/bf02af44bd11d182b40000e829fbfe/content.htm_ is not opening.

please help to resend the path

regards

Pradipta Sahoo

Former Member
Former Member
0 Kudos

Hi

See the list of planned order in MD04 , click on the same and release to production order.

Regards

Vinod

former_member197663
Participant
0 Kudos

Hi

I see in MS04 for the plant orders generated after LTP run. I want to convert these to operational planned orders, then I can see it in MD04.

Please suggest how to transfer planned orders from MS04 to MD04.