Hi
Can anyone suggest how to transfer planned orders generated from LTP(Long Term Plan) to Operational Plan?
Regards
Pradipta Sahoo
Dear Sahoo,
Check this,
http://help.sap.com/saphelp_erp60_sp/helpdata/en/92/bf02af44bd11d182b40000e829fbfe/content.htm
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Double click on the planned order in MS04 , new screen is open , in which one tab is there ---> convert planned order into production order. ---> click the same tab.
Regards
Vinod
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Sahoo,
You can transfer the simulative planned orders to operative planning using T Code MD43.
Check this,
Copying the Long-Term Planning Results to Operative Planning
Use
Once you have optimized the results of long-term planning, you can copy them to operative planning.
It is not only possible to copy the demand program to operative planning, you can also copy the planned orders firmed in long-term planning per material using the MRP transaction Interactive single-item planning.
When copying the results to operative planning, you can set the system to create purchase requisitions and delivery schedules instead of planned orders for materials procured externally.
Prerequisites
You must firm the simulative planned orders you want to copy to operative planning. You can firm planned orders by:
Making manual changes
Using the planning time fence
Setting a manual firming date
If, when copying the data to operative planning, you want the system to create purchase requisitions or delivery schedules for materials procured externally instead of planned orders, enter the appropriate indicators in the Create pur. req. and Schedule lines on the initial screen of single-item, interactive planning (in MRP).
When copying the results to operative planning, the system does not carry out any source determination. If you want the system to create delivery schedules and purchase requisitions to which a vendor has already been assigned, you must maintain the necessary master data in the Purchasing menu before carrying out the planning run in long-term planning.
http://help.sap.com/saphelperp60_sp/helpdata/en/92/bf02af44bd11d182b40000e829fbfe/content.htm_
Regards
Mangalraj.S
Dear Mangalraj
Thanks for your reply. Your suggested http://help.sap.com/saphelp_erp60_sp/helpdata/en/92/bf02af44bd11d182b40000e829fbfe/content.htm_ is not opening.
please help to resend the path
regards
Pradipta Sahoo
hi,
just remove the underscore @ the end
http://help.sap.com/saphelp_erp60_sp/helpdata/en/92/bf02af44bd11d182b40000e829fbfe/content.htm
Hi
See the list of planned order in MD04 , click on the same and release to production order.
Regards
Vinod
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.