on 06-07-2011 9:22 AM
Dear All,
I have a general query regarding Resource networks ( Newly added functionality in SCM 7.0 ) if anyone has worked on it.
Is it possible to include alternate resources in resource network.
For e.g. Say I have 2 machines M1, M2 feed to 3 distillers D1, D2 & D3.
M1 can feed to D1 or D2 depending on the availibility. However M2 can feed only to D3.
Can we have the first relation defined in a single resource network M1 ---> D1 OR D2.
OR
I need to have 2 resource networks defined:-
1. M1 --> D1
2. M1 --> D2
Thanks in advance for your help
Regards
Ameet
Yes, you can use resource network for this requirement.
Use PPDS Optimizer with resource network - it will take care of it.
Let me know if you have specific issue.
Vipul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.