Activity Rate Calculation at Production Order and Cost Estimate

Hi All,

A) I have created a cost estimate, where Activity Type is shoiwng as below values

Activity Type = MACH

Total Value= 1575 INR

Quantity = 3

I have uploaded the price of this activity in KP26 as 2100 INR, Now my Question is how system is Total Value, where as it is different from the rate in KP26

Please help me to understand.