Transportation time

Former Member
0 Kudos

DEAR ALL,

I want to add transportation time (2 days) in customer mommitment date.

Material aval date

Loading date

GR date

Transporation planning date.

Transportation duration i want to include this.

Many thanks.

Ram

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

In the transaction 0VTC maintain the transit time as 2 days .Maintain this route for your departure zone and destination zone with the shipping condition same as that in your customer master and the transportation group as in your material master in IMG --> logistics execution -->shipping -->basic shipping function -->Routes --> maintain route determination.

Now this transit time will be included in the scheduling.

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi

LE>Basic Shipping Functions>Routes>Define Routes>Define Routes & Stages.

There maintain the time under the clolumn "TransitDur" for ur route.

Regards

Madhu

Former Member
0 Kudos

Hi,

IMG >> SD >> Basic function >> Delivery scheduling & Transportation scheduling >> Maintain duration

Select your shipping point and double click on ROUTE left hand side and maintain duration

Kapil

Former Member
0 Kudos

Hi,

If my understanding of your issue is right, then you are looking to include the transporation duration of 2 days when you wanted to calculate the Confirmation date to the customer.

For this requirement, you need to define the duration as 2 days in the ROUTE (transit time) and that would help you to get the confirmation date based on the duration also (apart from other parameters).

I hope this helps you.

Regards,

Sampat