Sub-contracting External Processing PP-PI

hI,

I am trying to create sub-contracting order through SAP PP-PI.

I have a FG - X, with components X1 & X2.

I have 3operations and 3 phases in the Recipe for X.

The 2nd phase is having the control key for external processing, because of which i had to assign Purc.Info record to this phase.

( Pls note that its not allowing me to enter a PIR of material/vendor combination, hence had to create for Material Group/ Vendor).

Now when i Create and release a Process order for X, there is a Pur req created but it has no material, and i cant change anything in this Pur. req.

Please help.