Dear experts,

I will planning to do revaluation of actual activities prices at actual price but some time I am facing error at actual activities price.Equivalence no. is zero for activities type and cost center but equivalence no. is already maintained for the same in KP26.

Then need to change equivalence no. from 1 to some other no. like 11. then it will works.

But i am not calculating actual price on the basis of equivalence no.What will happen if i will delete equivalence no. from KP26(maintained it blank).

Whether this will impact to my revaluation of activity or from where equivalence no. is coming in KP26 by default as 1.

regards

RR

Accepted Solutions (1)

Accepted Solutions (1)

former_member588855
Active Contributor
0 Kudos

Hi Raman,

Actual Activity price calculation is done on the basis of actual quantity of activity confirmed by production people through co11n and captured in your cost center and splitting of cost on the such basis.

Equivalence no. comes into play when the system can't find the quantity confirmed.

Regards,

Divraj