Hi,

I have loaded the data from R/3 to BI via process chain but due to some reson it got stucked with yellow light and after certain amount of time got red. I repeated the process chain but now it is showing me 0 of 0 records and is running again for long duration. I checked process monitor also and it shows me following message : Info IDoc 1 : sent, not arrived ; Data passed to port OK . how to repair or rerun the process chain again so as not to miss the data ..

regards

SH

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

in the next process chain it has bring all the records...so no worries now..

Former Member
0 Kudos