Hi PM Gurus,

Can someone please let me know how to make the field "Activity Type" and "Planner Group" mandatory (Required Entry) in Maintenance Plan at screen level.

Cheers

Deepal

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Try this User Exit.

IPRM0004 Maintenance plan / item: Customer check for time "SAVE"

Regards,

Maheswaran,

Former Member
0 Kudos

Hi ,

If you do not want to go for user exit then you can also get it using transcation variants via tcode SHD0 ... for IP41 /IP02/IP42/IP43 Tcodes ..

Search this forum for steps as it was discussed many times ..