cancel
Showing results for 
Search instead for 
Did you mean: 

standar cost and product cost collector not updating the new price

Former Member
0 Kudos

Hi,

Created Standard cost estimate for one FG product and runned the product cost collector. Based on that consumption delivery everthing is made. Later on the work center and activity type changed in routing. Now i am trying to run the standard cost with new activity price (due to work center change) for the current period, system is showing only the previous rate(previous period) and it is not updating the new price becuase of already we have created the product cost collector.

Can any one give the suggestion for how to update the new price in standard cost as well as new price updation in product cost collector.

govind.

Accepted Solutions (0)

Answers (1)

Answers (1)

ajaycwa1981
Active Contributor
0 Kudos

Hi

1. If the original cost estimate was run in the current month - Then you cant re-release cost estimate unless you reverse it from CKR1

If the cost estimate was of previous months - then you can definetely release it again

2. In cost collector, you need to manually cost it again using the Preliminary costing feature... Your cost coll will then show 2 cost estimates i.e. One from Original date to current date-1, and 2nd from Current date to 31.12.9999

br, Ajay M