Dear PP gurus,
When system automatically does finite scheduling during overload, I get 3 warning messages.
Schedule conflict: Constraint is too late
Schedule conflict: Constraint is too early
Overlapping could not be maintained
I have 8 operations in which 6 overlaps with 7 and 7 overlpas with 8 (min send ahead)
But when finite scheduling,the 6th operation is scheduled before start of 4th operation when system does finite scheduling after 6th operation shows an overload.
My settings in OPDB , Scheduling controll - finite scheduling and insert opeartion ticked and 2 for closing gaps
SAPMRPAS03 - dispatch sequence with latest start date dispatch(I am using backward scheduling)
Dispatching functions
Sort operations to be dispatched-ticked
Consider operation sequence in the order-ticked
Operation date check-ticked,
Please help me figure out the issue,
Thanks in advance,
Sunanth V.Narayan
Is it because I have ticked insert operation in scheduling controll. I am not sure....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.