Repetetive Manufacu.

Former Member
0 Kudos

Dear Experts,

In My company Repetetive Manfuc. process is configured CO-PA is not configured we have two plants 1000 and 2000 Rem Profile is same for both plants but in my one plant 1000 every month i recieved an error message "Error determining the cost estimate" but in my second plant 2000 I not recieved any error i can do MFBF without error .Could you please confirm where I m woring in plant setting...or where I can do cost run for year..

Neeru

Accepted Solutions (1)

Accepted Solutions (1)

former_member186193
Active Contributor
0 Kudos

Dear,

If you have not executed the Preliminary Cost estimate for the Prod. Cost collector

OR

If ther is any change in the Routings (Addition/deletion of operations)

This error can be observed.

Execute the Transaction: MF30 and check

Hope it will help.

Regards,

Alok Tiwari

Former Member
0 Kudos

Dear Tiwari,

But every month why I require cost run and MF30 in only one plant...

Neeru

former_member186193
Active Contributor
0 Kudos

Dear,

Try it in both the plants and reply me what is happening.

Regards,

Alok Tiwari

Former Member
0 Kudos

my error is coming in one plant 'Error determining the cost estimate"

Neeru

former_member184655
Active Contributor
0 Kudos

Dear Neeru,

Check by performing a standard cost estimate and release using T code CK40N and then check in MFBF,whether the system is

displaying the same error.

If already a released cost estimate exists means do a reorganizing the same using CKR1 and then carryout CK40N and then

check in MFBF.

Check and revert

Regards

Mangalraj.S

Former Member
0 Kudos

GO to KKF6N is Product cost collector.IN there

specify a plant ,material names & run it cost collector,it shows fixed price is ma tined or not

goto KP26 fix the price

Answers (2)

Answers (2)

Anupam1143
Active Contributor
0 Kudos

HI

Check the REM profile attached to material of plant 1000 check under control data1> cost accounting > post activities>using preliminarey cost estimate or standard cost estimate.

compre both profiles which are assigned to materials of plant 1000 and 2000.

If it is preliminary cost estimate then once PCE is created it will not ask for standard cost estimate and valid thru whole period.

Check and revert

Regards

Anupam Sharma

Former Member
0 Kudos

Hi,

See below link, it will be useful for your problem

Regards / US