Production process problem

Hi all

kindly guide me how could we map production process through good issue and good receipt in textile industry.

as they are using multilevel production.

Thanks in Advance

Areeba Ali


Hi Areeba ,

In That Process , you have to maintain the Pipeline Concept.

The Output of One stage (Good Issue I) will become the Input of Next Stage (Good Receipt I).

You have to create the Warehouse as Stages.

Issue Raw Material to Knitting WHSE .

Now Receive the Knitted Material in the Other Whse (let Mending).

Then Again you have to Follow The same process for your each and every Stages of Production.

And Again , i am reminding you that , it will create a lot problem at the user end .

Also . . it is not the standard process of Production.

So Maintaining the WIP and Product Cost will also become an Issue.

Take care of that . . But i strongly not recommend the Good Issue and Receive for Production Process.