on 06-03-2011 9:14 AM
Hi All,
Some cost centesr are obsolete and mustn't be used in the creation of a Purchase Requisition (or Purchase Order).
Block
Could anyone suggest me how to do it?
Thanks a lot
G.
Hi
For PR - use ME_PROCESS_REQ_CUST
For PO - The badi is already given above
Ask your ABAPer to code the same
br, Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, you can build own logic for validation via badi ME_PROCESS_PO_CUST
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rossi,
If the cost centers are obselete, please go and lock the postings in the control tab of the cost center (KS02). By default system will issue a warning message if u use this in a purchase order. Now u can change this to a error message in message controls. This way u can disallow the usage of this cost centers in purchase order.
Best Regards
Vimal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rossi,
What is the Idea behind using the Cost Center in PR or PO, elaborate your requirement so that will help me to answer for you to achieve it.
rgd
YJ
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rossi ,
Please go to the Cost Center Master Data -> Control tab -> Block all the indicators..
You will not be able to use these Cost Centers in Future..
Regards
Sarada
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.