on 06-03-2011 6:46 AM
hi gurus,
Is it correect for system to check Min. rem. shelf life during reversal of good's issue ?
Secondly if not then how to prevent the system to do that as in my case it is checked during 262.
Let's say SLED is 15.06.2011 and min rem. shelf life is 3 days
now when i do the goods issue on 14.06.2011 system allows me to issue but if i reverse that same document on 14th, system is rejecting the reversal saying shortfall of some days against remaining shelf life.
Hi,
Compare shelf life expieration check for both movement types (261 & 262) in transection omjj.
Regards,
Dhaval