Hi Experts,

I am trying to look at order cost plan in CN41N. but i am not knowing from where this value is picking. when i see the order the value is showing some thing other than that seen in CN41N. Can any one please help me in finding where does this order cost plan come from for report.

Thanks,

Satish.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

It is nothing but the plan cost that comes from the network costing i.e. cost planned for the activities that fall under a particular network. Which order are you seeing and comparing this column with?