on 06-02-2011 12:44 PM
Hi Everyone,
We have Charm configured in our landscape, where in R/3, ECC,SRM systems are connected.
We have scheduled job from SCMA for all the these 3 systems which will run every 1 hr. When it runs all the Charm request in the status "to be tested" will be moved to the Quality system. This is the scenario. Now the problem is that, the job runs successfully in ECC & SRM but in R/3 it is failling intermitently. Sometime it runs good but sometimes it is failing giving the error message:
Status entry in TPSTAT failed
Import error. Check TMS Alert Viewer in target system
Alert viwer:
TP_INTERFACE_ERROR
TP_INTERFACE_ERROR
TP_INTERFACE_ERROR
CREATE_ENQUEUE_FAILED
CREATE_ENQUEUE_FAILED
i logged in OS (IBM AIX) level and found, 3 tp process are running at the same time. is this the problem why iam getting the error in importing request from Development to Quality or something else? why it is not happening for ECC and SRM?
Please let me know how to analyse this and resolve
Thanks & Regards,
Siva
i appreciate any inputs here
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Deepthi,
thanks for your response. i checked the table you have specified here. When i checked the table i found few entries related to some charm Project. I checked it the SCMA tcode in Charm if there is any job got failed during the time specified in the table entries but did not find any. But after sometime the table entries gone by itself. what could be the reason.
also, i found 4 - 5 tp processes running in the system at the same time since many maintenance cycle's jobs have been scheduled at the same time. this can be a reason for the failure? any idea
User | Count |
---|---|
82 | |
10 | |
10 | |
9 | |
6 | |
6 | |
5 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.