sample managmnet

Sir,

Pls see our procuement scenarion

1.Sample request as a po

2.Sample inspection with complete inspection

3.If sample is approved normal po is raised

4.Inspection on Gr in selective manner

so pls tell me how we can bring sample concept in QM area

Thanks in advance

Faisal

Former Member replied

Best Way, use source inspection . Maintain GR/Source inspection control setting in control key as:

GR for rejection > Goods receipts not allowed

GR control/Batch > Create new inspection lot

The only thing is I have not used physical sample and source inspection together, I am not sure if any implications are there for reserved samples when source inspection is rejected, though I think there should not be any. you can run a scenario and check.

0 View this answer in context