Hi,

I´m planning to do a remote client copy via SCC9. But I´m not sure about the working of parallel processes. I´ve defined a RFC Group in the RZ12 but the different parameters are automatically introduced.

Activated (0 or 1) 1

Max. Requests in Queue (%) 5

Max. No. of Logons (%) 90

Maximum No. Separate Logons(%) 25

Max. Number of WPs Used (%) 75

Minimum Number of Free WPs 1

Max. No. of Comm. Entries (%) 90

Max. wait time 15

If I want to do the most faster copy via SCC9 I need to use the max number of WP avalaible, but I´ve need to leave 3 WP free It´s correct,this?

Then If I´ve 15 WP of DIA, for what the client copy uses the DIA WP I need to put in Minimum Number of Free WPs to 3 and in the paramater Max. Number of WPs Used (%) 75

How can I resolve this?

More thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member

Ruben

You can set the parallel processing in RZ12. This will help in processing things parallely on all available application servers.

Regards

Vivek

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

I will suggest you to use Background WP for client copy than DIA WP.

It is more convinient.

Regards,