I want to trigger deployment in SPP module..I have maintained lead time of 2 days in transportation lane..I want system should take 6 days demand and deploy all the 6 days quantity today..

For this what setting i need to do..i have maintained maximum planning horizon in the deployment service profile as 6 dyas..but system is taking only 2 days demand into consideration..

kindly do the needful