on 06-01-2011 11:57 AM
Hello,
i'm facing a strange behavior in BI system. We have a schedule via DB12 for daily backup (in TSM) and during last days for two times we have no backup. The problem is that there is no job log in SM37 for those days and also i did not found any error log in system.
Any idea???
Regards,
Dimitrios
Are DB jobs visible in SM37 up until (the day before) the jobs in question did not run? Did the job continue to run every day afterwards?
Were these DB12 jobs visable in CPS?
Could someone have deleted or the jobs manually?
Are you sure that the DB12 jobs did not run and the backup for those 2 days does not exist?