on 06-01-2011 6:32 AM
Hello Friends ,
Business requirement is i receive material directly to sales order and do the PGI for the same , we are not a manufacturing unit .
issue is
i have booked my material to Sales Order and my material becomes SPECIAL STOCK E , now when i do PGI for the same SALES ORDER the same stock should be picked but it is showing you have 0 material available .
please guide how to do PGI for SALES ORDER Stock .
Thanks
Aditya
Hi,
As far as my understanding
you can do GRN with movement type 101
Then you transfer stock from unrestricted stock to sales order stock by movement type 413 E and then delivery & PGI
Kapil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In MMBE , pls check if it is showing as Sales Order Stock with the specified Quantity. Then you have to check the storage Location which is defined as default for the Shipping Point & Plant in T Code OVL3.
Best Regards,
Ankur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
1.Please check the movement type in the delivery, in the "goods movement data" tab page i believe it should be 601 E.
2. If 1 is true check if you have assigned the "special stock" E in the item category.
3. For uploading the stock against the sales order, I believe you are using movement type 521 E. Please check if 521 movement type is assigned in the schedule line, in "Movement Type 1-Step" field.
Please let me know your feedback.
Regards
Aadesh Kamat
hi,
The movement type for sales order stock should be 601E. I assume that you know, the special stock indicator "E" is 6 column right to the movement type 601 on the "goods movement data" tab page in the delivery.
If the special stock indicator is not there check the "MRP" veiws in the material master. "MRP1","MRP3".
Check the following fields:-MRP TYPE
AVAILABILITY CHECK
STRATEGY GROUP
Check the movement type you are using during GRN, MIGO. it should be 521 E. Assign it in the scedule line as mentioned earlier.
Regards
Aadesh Kamat
Edited by: aadesh123 on Jun 1, 2011 8:57 AM