Hi Gurus,
I working on a DP BOMs scenario. We have multi-level BOMs going up to 6 levels. When I generate a DP PDS using SNP PDS (T Code - /SAPAPO/CURTO_GEN_DP), the system only picks components at the last level.
For e.g. If Product ABC has the following components: -
1) A
2) B
3) C
C1
(ii) C2
When I generate DP PDS, it picks up only the following components - A, B, C1, C2. Is there any BADI to ensure that the system picks up Assembly C as well?? (Basically, I want the following components in DP PDS - A, B, C, C1, C2).
Any responses will be appreciated.
Regards,
Shiv
Could you please check if SAP Note No. 1372237 is present in your system.
Rgs
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.