Regeneration / recreation of the Task List

Former Member
0 Kudos

Hello Experts,

I have a project in SOLMAN with activated CHARM and the Task List.

The task list still has over 50 transport requests

The client's request is to recreate pr create a new task list for the same project.

What can happen with the ransport requests assigned to the "old" task list after creation of a new one?

Please advice

Thanks!!!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Per my understanding, one project can only have one task list. You will need to close the existing task list before opening a new one.

That said, if you force close your existing task list, you can open a new one, and all existing open transports will automatically attach themselves to the new task list. Any open change tickets however, will go in a "fuzzy" state.

Please review note 1071412 for more details.